Installation Qualification of High Speed Linear Vial Washing Machine protocol is to establish documentary evidence to ensure that the Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) received matches the Design specification.
The signing of this approval page of the Protocol indicates agreement with the qualification approach described in this document. If a modification to the qualification approach becomes necessary, an addendum shall be prepared and approved. The protocol cannot be executed unless approved by the following authorities.
This Installation Qualification protocol for Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) has been reviewed and approved by the following persons:
FUNCTION
NAME
DEPARTMENT
SIGNATURE
DATE
PREPARED BY
QUALITY ASSURANCE
REVIEWED BY
PROJECTS / ENGINEERING
REVIEWED BY
PRODUCTION
APPROVED BY
QUALITY ASSURANCE
2.0
OVERVIEW:
2.1
OBJECTIVE:
The objective of developing and executing this protocol is to collect sufficient data pertaining to the Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) and define the qualification requirements and acceptance criteria for the unit. Successful completion of these qualification requirements will provide assurance that the Automatic High-Speed Linear Vial Washing Machine was installed as required in the manufacturing area.
2.2
PURPOSE:
The purpose of this protocol is to establish documentary evidence to ensure that the Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) received matches the Design specification and also to ensure that it is properly and safely installed.
2.3
SCOPE:
This Protocol is applicable to the installation of an Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) at the Dry injection manufacturing facility in XYZ Pharmaceutical & the subsequent documentation.
2.4
RESPONSIBILITY:
The following shall be responsible; Departmental Head: Mention their Responsibilities
2.5
EXECUTION TEAM:
The satisfactory installation of the Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) shall be verified by executing the qualification studies described in this protocol. The successfully executed protocol documents that the Automatic High-Speed Linear Vial Washing Machine with two conveyor belts (one for loading the vials to the washing machine and another for unloading from the washing machine) is installed and is satisfactorily integrated.The execution team is responsible for the execution and installation of Automatic High-Speed Linear Vial Washing Machine Execution team is comprised of:
DEPARTMENT
DESIGNATION
NAME
SIGNATURE
DATE
PROJECTS / ENGINEERING
PRODUCTION
QUALITY ASSURANCE
3.0
ACCEPTANCE CRITERIA:
3.1
The equipment shall fulfill all the selection criteria and its individual application
3.2
The equipment shall comply with the specification mentioned in the user requirement specification.
3.3
It shall be complying with all the designed specifications.
3.4
The Material of Construction (MOC) shall be complying with the test certificate.
3.5
All supporting electrical and non-electrical utilities of specified capacities are to be near the place of installation.
4.0
REVALIDATION CRITERIA:
The machine has to be revalidated if
💡Any major changes in system components affect the performance of the system. 💡After a major breakdown maintenance is carried out. 💡As per the revalidation date and schedule.
5.0
INSTALLATION QUALIFICATION PROCEDURE:
5.1
SYSTEM DESCRIPTION
The Principle of Automatic High-Speed Linear Vial Washing Machine is designed for washing of vials (5ml to 30ml) and these two conveyor for loading vials to the washing machine and unloading them from the washing machine.
TheAutomatic High-Speed Linear Vial Washing Machine works on the principle of jet washing of the individual vials in a mouth-down position by a series of jets.
The vials are loaded on the unloading station by placing a tray of vials on it. The complete layer of the vials is pushed out to the machine platform through a loading conveyor.
The vials go to in feed lifter with the help of in feed conveyer. Then this in-feed lifter carries the vials into the individual pockets.
After vials go into the pockets channel runs to the backside (Anticlockwise). During this process, the in-feed lifter comes back and carries other vials for washing continuously.
The index channel of vials carries forward at a time. During each stoppage of this movement, the nozzle manifold raises up and a nozzle enters the mouth of each individual vial.
A solenoid valve in the water and air lines is now activated and a jet of air/water hits the inside of the vial to thoroughly clean it.
An external cleaning station is also provided. The standard washing sequence provided is as under:
1st wash: Compressed air.
2nd wash: Re-circulated water.
3rd wash: Re-circulated water.
4th wash: Compressed air.
5th wash: Purified water.
6th wash: Compressed air.
7th wash: Purified Water.
8th wash: Compressed air.
9th wash: WFI.
10th wash: Compressed air.
These washed vials are then taken away from the pockets with the support of a vial guide plate and come out on the out-feed lifter.
The outfeed lifter comes down and the washed vials (12 vials at a time) are transferred to the outfeed conveyor for further process.
Equipment Details:
Equipment Name: Automatic High-Speed Linear Vial Washing Machine
Make: Make Name
Model No. : XYZ
Capacity: 150 vials/Minute (5ml to 30ml vials)
5.2
INSTRUCTION FOR FILLING THE CHECKLIST
5.2.1
In case of the compliance of the test use the word ‘Complies’ otherwise use ‘Does not comply‘ to indicate non-compliance.
5.2.2
To identify equipment and utilities components, use “yes” for presence and “No” for absence of identity.
5.2.3
Give the detailed information in the summary and conclusion part of the Installation Qualification report.
5.2.4
Whichever column is blank or not used ‘NA’ shall be used.
5.3
INSTALLATION CHECKLIST:
The installation checklist is as follows:
Sr. NO.
STATEMENT
YES / NO
CHECKED BY(SIGN)
DATE
Verify that the “As Built” drawing is complete and represents the design concept.
Verify that major components are securely anchored and shock proof.
Verify that there is no observable physical damage.
Verify that there is sufficient room provided for servicing.
Safe electrical connections, Water lines and Compressed air are fitted.
Equipment identification nameplate visible.
Verify that all piping and electrical connections are done according to the drawings.
Safe electrical connections, Water lines, and Compressed air are fitted.
Wiring diagram affixed to inside section of control panel.
Units installed on foundation are secure in place as per manufacturer’s recommendations.
Check the dimensions for the infeed conveyor: 1500 mm (L) X 345mm (W)
Check the dimensions for the outfeed conveyor: 340 mm (L) X 900mm (W)
5.4
IDENTIFICATION OF MAJOR COMPONENTS:
To Verify that major components as identified below comply with the desired specifications.
System components
Design Specifications
Complies / does not comply
Checked By (Sign.)
Date
Equipment description
Name: Automatic High-Speed Linear vial washing machine Make: Ambica Engineering works Model: AHLVW – 150 Output: 150 vials/minute of 5ml to 30 ml
Reduction type with helical gear drives AMBICA make
Conveyor drive gear motor
Make- Ambica, 0.5 HP
Filter housing
Four no.
Washing Nozzle
12 x 10
Vial pocket
12 x 40
Limit switch
Four no., AC 15 at 415 volt, 1.5Amp., Make – Grunfors
5.5
VERIFICATION OF MATERIAL OF CONSTRUCTION:
Verify the material of construction from test certificates.
Sr. No.
Components
MOC
Method of verification
Checked By sign./Date
1.
Washing Needles
SS 316
Visually with test certificate
2.
All Tanks
SS 316
Visually with test certificate
3.
Machine frame and structure
SS 304
Visually with test certificate
4.
All side covers
SS 304
Visually with test certificate
5.
Vial pocket
HDPE
Visually with test certificate
6.
All prism patty
UHMW
Visually with test certificate
7.
Pusher
UHMW
Visually with test certificate
8.
Loosening patty
UHMW
Visually with test certificate
9.
Conveyor belt
SS 304 wire mesh type
Visually with test certificate
10.
Pockets Channel
SS 304
Visually with test certificate
11.
Main Pocket drive chain
SS 316
Visually with test certificate
12.
Pocket drive chain sprocket
Nylocast
Visually with test certificate
13.
Drive cam
Harden material
Visually with test certificate
14.
Indexing drive cam
Harden material
Visually with test certificate
15.
All shaft
SS 304
Visually with test certificate
16.
All pipe fittings for the drain
SS 304
Visually with test certificate
17.
All rubber gasket
Silicon
Visually with test certificate
18.
All Tanks
SS 316
Visually with test certificate
19.
All pipe fittings
SS 316 with Silicon
Visually with test certificate
5.6
IDENTIFICATION OF SUPPORTING UTILITIES:
Identify and record the supporting utilities and their details in the following tables:
UTILITY
PROPERLY IDENTIFIED & CONNECTED (YES/NO)
CHECKED BY (SIGN)
DATE
1) Electricity:Specification: 415 VAC, 3 Ph.
2) Compressed air (20CFM)0 – 4 Kg/cm2
3) Recycle water (400 Ltrs./hour)0 – 4 Kg/cm2
4) Purified water (400 Ltrs../hour)0 – 4 Kg/cm2
5) Purified water (400 Ltrs../hour)0 – 4 Kg/cm2
6) WFI (300 Ltrs./hour)0 – 4 Kg/cm2
5.7
IDENTIFICATION OF SAFETY FEATURES:
Identify and record the safety features (if any) and their function in the following tables:
Sr.No.
Safety feature Description
Function
Identified By(Sign)
Date
1.
Check for the overload safety devices
The electric circuit should be provided with a miniature circuit breaker. for motor safety.
2.
Check for Earth connection
Earth connection should be provided properly.
3.
Two Emergency stop
One on the main panel and another at the backside cover for Equipment and operator safety.
4.
Discharge vial jam
Limit switches should be provided inside the indexing drive box. For Equipment safety.
5.
Pusher vial jam
A limit switch should be provided on the pusher clutch. For Equipment and product safety.
6.
Lifter vial jam
A limit switch should be provided on the lifter clutch. For Equipment and product safety.
7.
Infeed vial jam
A limit switch should be provided on the Infeed drum clutch. For Equipment and product safety.
5.8
IDENTIFICATION OF STANDARD OPERATING PROCEDURE (SOP)
Operation and cleaning of Automatic High-speed linear Vial washing machine
1.
Operation and cleaning of Automatic High speed linear Vial washing machine
2.
Preventive maintenance of Automatic High-speed linear Vial washing machine
5.9
IDENTIFICATION OF COMPONENT TO BE CALIBRATED:
Identify and record the instruments to be calibrated in the following tables:
Sr.No.
Name of the Instrument
Location
Specification
Identified By(Sign
Date
1.
Pressure gauge
Compressed air supply line
0 – 4 kg/cm2 Make: Micro
2.
Pressure gauge
Recycle water supply line
0 – 4 kg/cm2 Make: Micro
3.
Pressure gauge
Purified water supply line
0 – 4 kg/cm2 Make: Micro
4.
Pressure gauge
Purified water supply line
0 – 4 kg/cm2 Make: Micro
5.
Pressure gauge
WFI supply line
0 – 4 kg/cm2 Make: Micro
5.10
VERIFICATION OF DRAWING AND DOCUMENTS:
The following documents are reviewed and attached as listed below:
Sr. No.
DRAWING AND DOCUMENT DETAIL
CHECKED BY (SIGN)
DATE
5.11
ABBREVIATIONS
The following Abbreviations are used in the installation qualification protocol of the Automatic High-speed linear Vial washing machine.
P & I: Piping and instrumentation VFD: Variable frequency drive UHMW: Ultra high molecular weight polyethylene HDPE: High-density polyethylene VWM: Vial washing machine
5.12
DEFICIENCY AND CORRECTIVE ACTION (S) REPORT (S)
The following deficiency was identified and corrective actions were taken in consultation with the validation team.
Description of deficiency:
Corrective action(s) taken:
Reviewed By:
Date
5.13Annexure(s):
Sr.No.
Annexure No.
Title of Annexure
6.0
INSTALLATION QUALIFICATION FINAL REPORT:
All the IQ data sheets and discrepancy reports shall be reviewed by the validation team to prepare a summary report. The summary of IQ shall be used to draw a conclusion for approval of the installation qualification report.
6.1
SUMMARY
6.2
CONCLUSION
6.3 FINAL REPORT APPROVAL
It has been verified that all tests required by IQ of High-Speed Linear Vial Washing Machine protocol are completed, reconciled, and attached to this protocol or included in the qualification summary report. Verified that all amendments and discrepancies are documented, approved, and attached to this protocol.
Signature in the block below indicates that all items in this qualification report of the Automatic high-speed linear Vial washing machine have been reviewed and found to be acceptable and that all variations or discrepancies have been satisfactorily resolved.
Naresh Bhakar is the Founder and Author at Pharmaguddu.com, bringing his extensive expertise in the field of pharmaceuticals to readers worldwide. He has experience in Pharma manufacturing and has worked with top Pharmaceuticals. He has rich knowledge and provides valuable insights and data through his articles and content on Pharmaguddu.com. For further inquiries or collaborations, please don’t hesitate to reach out via email at [email protected].