Learn about the Installation Qualification Protocol for Blister Packing Machine along with Annexures. The purpose of this protocol is to establish documentary evidence to ensure that the Blister packing machine received matches the Design specification and also to ensure that it is properly and safely installed.
Serial No.
Item Description
1.0
PROTOCOL APPROVAL
2.0
OVERVIEW:
2.1
Objective
2.2
Purpose
2.3
Scope
2.4
Responsibility
2.5
Execution Team
3.0
ACCEPTANCE CRITERIA
4.0
REVALIDATION
5.0
INSTALLATION QUALIFICATION PROCEDURE
5.1
Equipment Description
5.2
Instruction for Filling the Checklist
5.3
Installation Check-List
5.4
Identification Of Major Components
5.5
Identification of Supporting Utilities.
5.6
Identification Of Safety Feature(s)
5.7
Identification Of Standard Operating Procedure
5.8
Identification Of Component to be Calibrated
5.9
Verification of Drawings and Documents.
5.10
Deficiency And Corrective Action(s) Report(s)
5.11
Annexure (s)
6.0
INSTALLATION QUALIFICATION FINAL REPORT
6.1
Summary
6.2
Conclusion
6.3
Final report approval
1.0
PROTOCOL APPROVAL:
This Installation Qualification Protocol for Blister packing machine has been reviewed and approved by the following persons:
FUNCTION
NAME
DEPARTMENT
SIGNATURE
DATE
PREPARED BY
QUALITY ASSURANCE
REVIEWED BY
PROJECTS / ENGINEERING
REVIEWED BY
PRODUCTION
APPROVED BY
QUALITY ASSURANCE
2.0
OVERVIEW :
2.1
OBJECTIVE:
To perform the Installation Qualification of the Blister packing machine to be used for the Primary packing of tablets.
2.2
PURPOSE:
The purpose of this protocol is to establish documentary evidence to ensure that the Blister packing machine received matches the Design specification and also to ensure that it is properly and safely installed.
2.3
SCOPE:
TheScope of this protocol is limited to the Installation Qualification of the Blister packing machine XYZ Pharmaceuticals.
2.4
RESPONSIBILITY:
The following shall be responsible; Quality Assurance Officer/ Executive – For preparation of protocol/ Execution Projects, Engineering Head – For execution, Production Head – For execution support, Quality Assurance Head – For adequacy and final approval
2.5
EXECUTION TEAM:
The execution team is responsible for the execution of this protocol. The execution team comprises of:
DEPARTMENT
DESIGNATION
NAME
SIGNATURE
DATE
PROJECTS
PRODUCTION
QUALITY ASSURANCE
3.0
ACCEPTANCE CRITERIA:
3.1
The equipment shall fulfill all the selection criteria and its individual application
3.2
The equipment shall comply with the specifications mentioned in DQ.
3.3
It shall comply with all the designed specifications.
3.4
The Material Of Construction ( MOC) shall comply with the specification.
3.5
All supporting utilities of specified capacities are to be near the place of installation
3.6
All the specified installation checks are to be complied.
3.7
All the related drawings and documents shall be checked and complied for availability and authenticity.
3.8
All Standard Operating Procedures are to be identified.
4.0
REVALIDATION CRITERIA:
The machine has to be revalidated if:
1. Any major changes affect the performance of the equipment. 2. After a major breakdown maintenance is carried out. 3. As per the revalidation date and schedule
5.0
INSTALLATION QUALIFICATION PROCEDURE
5.1
EQUIPMENT DESCRIPTION:
Equipment Name
Blister packing machine
Supplier / Manufacturer
XYZ Company
Dimension (LXW)
200 X 100 (or As per URS)
Volumetric capacity (Tab of max 10mm )
2100 Tab/min (or As per URS)
Working Capacity
300 Blisters/min (or As per URS)
Maximum PVC film width
210 mm (or As per URS)
Maximum PVC film reel diameter
440 mm (or As per URS)
Maximum Aluminium foil reel diameter
206 mm (or As per URS)
Maximum aluminium foil width diameter
210 mm (or As per URS)
Average power consumption
7.5 KVA (or As per URS)
Air Pressure Required
540 NI /min at 8 Kg/Sq. Cm (or As per URS)
Cooling water Flow Rate
2 lit / min at 15 to 20 ºC (or As per URS)
Model
Rotovac -210V (or As per URS)
Serial no.
(or As per URS)
Location
Primary packing of tablets (Area Name)
Blister packing machine comprises of following components.
Hopper
Vibrator
Feed roller
Forming Roller(Assembly )
Feeding Box
Web guide track
Sealing Roller (Assembly)
Indexing roller
Guide roller
Machine panel & cover
Trim chute
Embossing Unit
Perforation Unit
Pack pick and place assembly
Batch Code printing unit
Punching station
Conveyer belt
Safety limit switch
Emergency switch
The Blister packing machine Rotovac-210V is an automatic blister packing machine utilized to pack tablets in blister packs. It operates on compressed air-assisted forming and rotary sealing The PLC controls the multiple functions of the machine. The thermoforming material loaded on the reel feed is drawn by a motor and is fed to the pre-forming heater through a dancing arm. The pre heated base film moves on the forming station where the blister cavities are formed on plastic zed base film. The blister cavities are formed by Vacuum The formed blister web is wrapped around the indexing roller fed through a small guide plate. The batch coding is done by a pneumatically operated system from where the coded web is transferred to a mechanical-driven perforating station. These embossed and perforated webs are then transferred to the punching station through an indexing Unit operated mechanically. All the operational controls and sequences of the machine are arranged by a Man-Machine Interface mounted conveniently located in front of the machine and mechanical cams with a limit switch which determines the positional accuracy of the machine with the feed pack.
5.2
INSTRUCTION FOR FILLING THE CHECKLIST
5.2.1
In case of compliance of the test use the word ‘Complies’ otherwise use ‘Does not comply‘ to indicate non-compliance.
5.2.2
For identification of the components of the equipment and utilities use the word ‘’yes’’ to show its presence and use ‘No’ to indicate the absence of the identity
5.2.3
Give detailed information in the summary and conclusion part of the Installation Qualification report.
5.2.4
Whichever column is blank or not used ‘NA’ shall be used.
5.3
INSTALLATION CHECKLIST: The installation checklist is as follows:
SR. NO.
STATEMENT
YES / NO
CHECKED BY (SIGN)
DATE
01.
Verify that the “As Built” drawing is complete and represents the design concept.
02.
Verify that major components are securely anchored and shockproof.
03.
Verify that there is no observable physical damage.
04.
Verify that there is sufficient room provided for servicing.
05.
Verify that all piping and electrical connections are done according to the drawings.
06.
All-access ports are examined and cleared of any debris.
07
Safe electrical connections.
08.
A wiring diagram affixed to the inside section of the control panel.
09.
Are Equipment identification nameplates visible?
10.
Units installed on the foundation are secure in place as per the manufacturer’s recommendations.
5.4
IDENTIFICATION OF MAJOR COMPONENTS:
Describe each critical component and check them and fill out the inspection checklist.
EquipmentsComponents
Design Specification
Complies / Does Not Comply
Checked By (Sign)
Date
AC Motor
BONFIGLIOI Star – Delta, 1HP/0.75Kw, 1500 RPM
Gear Box
Reduction 10:1 A – 162
Temperature controller (PHR)
PXW 40 AY2-1 BC75
Temperature controller (PSR)
PXW 40 AY2-1 BC75
PLC
Make: XYZ Company, Fx2N-64Mt
MMI
BEJAR E615
Invertor
XYZ Company
Vibrator
Vibromex 230 V
Color sensor
Visolux DK 20, U8=10.30VDC
Pressure Gauge (FRC)
Festo 0 to 16 Bar TYP concentric
Pressure Gauge(RELEASE )
Festo 0 to 16 Bar TYP concentric
Pressure Gauge(SUCTION)
Festo 0 to 16 Bar TYP concentric
Pressure Gauge(SEALING )
Festo 0 to 16 Bar TYP concentric
Vacuum Gauge
Festo 0 to -1 Bar
Infeed Motor
Remi ( 1/ 20 HP)
5.5
IDENTIFICATION OF SUPPORTING UTILITIES:
UTILITY
PROPERLY IDENTIFIED & CONNECTED (YES/NO)
CHECKED BY (SIGN)
DATE
1. Electricity :3 Phase 440 Volts 50Hz
2. Compressed air 8kg/cm2
3. Chilled water 15- 20ºC
5.6
IDENTIFICATION OF SAFETY FEATURES :
Identify and record the safety features (if any) and their function in the following tables :
Safety Features Description
Function
Identified By (Sign)
Date
1. Safety guard
The machine will stop if not locked properly.
2. Earthing
To avoid electrical shocks due to leakage current.
3. Emergency stop button
To stop the machine if the problem appears in running condition.
4. Micro switch for PVC film
The machine will not operate if the PVC roll is finished.
5. Hopper lid
To prevent the entry of dust or any foreign particles in the hopper
5.7
IDENTIFICATION OF STANDARD OPERATING PROCEDURE (SOP)
The following Standard Operating Procedures were identified as important for effective performance.
1
Operation of Blister packing machine
2
Cleaning of Blister packing machine
3
Preventive maintenance of the Blister packing machine
5.8
IDENTIFICATION OF COMPONENT TO BE CALIBRATED
1. Temperature sensors 2. Pressure gauges
5.9
VERIFICATION OF DRAWING AND DOCUMENTS:
The following documents are reviewed and attached as listed below:
Sr. No.
DRAWING AND DOCUMENT DETAIL
CHECKED BY (SIGN)
DATE
5.10
DEFICIENCY AND CORRECTIVE ACTION(S) REPORT(S)
The following deficiency was identified and corrective actions were taken in consultation with the Engineering Department.
Description of deficiency :
Corrective action(s) taken :
Reviewed By:
Date:
5.11 Annexure(s):
Sr.No.
Annexure No.
Title of Annexure
6.0
INSTALLATION QUALIFICATION FINAL REPORT:
6.1
SUMMARY:
6.2
CONCLUSION :
6.3 FINAL REPORT APPROVAL
It has been verified that all tests required by this protocol are completed, reconciled, and attached to this protocol or included in the qualification summary report, and verified that all amendments and discrepancies are documented, approved, and attached to this protocol.
The signature in the block below indicates that all items in this qualification report of the Blister packing machine have been reviewed and found to be acceptable and that all variations or discrepancies have been satisfactorily resolved.
Naresh Bhakar is the Founder and Author at Pharmaguddu.com, bringing his extensive expertise in the field of pharmaceuticals to readers worldwide. He has experience in Pharma manufacturing and has worked with top Pharmaceuticals. He has rich knowledge and provides valuable insights and data through his articles and content on Pharmaguddu.com. For further inquiries or collaborations, please don’t hesitate to reach out via email at [email protected].