Responsibilities of the Validation Team to Meet the cGMP Compliance

👤 Written by: Pankaj Sharma
Quality Control, Quality Assurance Specialist | Industry Experience

✓ Reviewed by: Pankaj Sharma - Quality Control Specialist
Reviewed for QC, QA accuracy, laboratory practices, analytical methods, and technical Documents

📅 Last Updated: November 16, 2026

One coordinator, preferably the Quality Assurance (QA) manager, leads the validation team. A task force of department managers works closely to sets the scope, priorities and acceptance criteria and approves protocols and reports. Working groups carry out the work, and QA approval stays independent of execution, as 21 CFR 211.22 and EU GMP Annex 15 expect.

Objective

A validation team is a group of people from quality assurance (QA), production, engineering, quality control (QC) and other departments. It plans, executes and approves validation work. This Standard Operating Procedure (SOP) defines the responsibilities of the validation team to meet the cGMP compliance, which means current good manufacturing practice (cGMP). It covers planning, execution, approval and the upkeep of the validated state.

1.0 Scope

The SOP applies to all validation activities of equipment, utilities, processes, cleaning and computerised systems at the site. It covers the departments that take part in validation and the outside vendors who work for them.

2.0 Definitions and Abbreviations

  • Task force (certification team): the group of department managers that decides the scope, priorities, acceptance criteria and approvals.
  • Working group: the group of dedicated personnel that executes the validation work.
  • VMP: validation master plan.
  • User Requirement Specification (URS): user requirement specification.
  • Design Qualification (DQ), Installation Qualification (IQ), Operational Qualification (OQ), Performance Qualification (PQ): design, installation, operational and performance qualification.
  • FAT, SAT: factory acceptance test and site acceptance test.
  • Computer System Validation (CSV): computerised system validation.
  • Technical services manager: the manager responsible for engineering and plant services support to validation.

3.0 Responsibility

Department heads and contractors must follow this SOP. The QA manager develops and maintains the validation programme and is responsible for SOP compliance.

4.0 Accountability

The core committee is accountable for resources and decisions that affect validation. In a four-tier team, it consists of the heads of QA, production, engineering (wherever applicable) and QC.

5.0 Procedure: Responsibilities of the Validation Team to Meet the cGMP Compliance

The procedure names the coordinator, the task force that decides, the working groups that execute and the planning of the work.

Flow chart of the responsibilities of the validation team to meet the cGMP compliance, from team roles to equipment work and approval

5.1 Validation Coordinator

QA manager coordinates all validation activities from planning to the final report. The coordinator must not carry out the tests that QA then approves, because execution stays with the working groups. In the four-tier model, the task-force leader is a QA in-charge, and the coordinator is a QA representative.

5.2 Validation Task Force/Certification Team

The task force decides what is validated and how it is approved. It consists of the managers of the departments involved and the approved outside vendors (if applicable). The list below is an example, and the role names vary by site. No pharmacopoeia or regulator prescribes these titles. Many sites place calibration and technical services under Engineering/Maintenance, and some validation-team schemes name the Head of Engineering (wherever applicable) and an Engineering representative instead. Typical members are:

  • Quality assurance manager
  • Production manager
  • Technical services manager
  • Product development manager
  • Calibration manager
  • Quality control manager
  • Approved vendors (outside)

5.3 Responsibilities of the task force

  • Scope of validation, based on a documented risk assessment under International Council for Harmonisation (ICH) Q9(R1)
  • Validation priorities
  • Acceptance criteria
  • Approving of validation protocols and reports
  • Validation change control

5.4 Validation Working Groups

The working group executes the work that the task force has decided and approved. The executive part of the validation work is delegated to dedicated personnel:

  • A member of the validation task force
  • Representatives from relevant departments
  • A representative from quality assurance
  • A representative from technical services
  • A representative from the product development laboratory
  • A representative from quality control
  • A representative from the vendor (outside)

5.5 Validation Planning and Scheduling

The coordinator plans the schedule with the departments according to the VMP, which is approved by QA, validation, production and engineering and is updated through the project. The planning items and their planners are:

  • Manpower resources: planned by the task force, with the department managers.
  • Document preparation: planned by the coordinator and the validation or engineering team.
  • Field execution: planned by the working group.
  • Calibration: planned by the calibration manager.
  • Lab support: planned by the QC manager.
  • Test and balance/filter certification: planned by the technical services manager.
  • Start-up and commissioning: planned by engineering with the vendor.

Regulatory Basis of the Validation Team’s Duties

The FDA’s 2011 process validation guidance recommends an integrated team of process engineering, industrial pharmacy, analytical chemistry, microbiology, statistics, manufacturing and QA, and it describes three stages: process design, process qualification and continued process verification.

Under 21 CFR 211.22 the quality unit must approve or reject procedures and specifications that affect product quality, and its responsibilities must be in writing and followed. EU GMP Annex 15 (operational since 1 October 2015) expects the VMP to define the validation policy, organisational structure, functions, responsibilities and timetable, and it bases the scope of qualification and validation on a documented risk assessment.

ICH Q9(R1) (January 2023) adds guidance on controlling subjectivity in these risk assessments, so the task force must document how each risk decision was reached.

Team Duties Across the Validation Lifecycle

Each stage has an owner, and QA approves the report of one stage before the next stage starts.

StageMain duty of the team
URSThe user department states what is needed, without prescribing how it is met
DQ, IQ, OQEngineering and the vendor execute, and QA reviews and approves
PQThe execution team shows that the equipment runs the process to the URS under normal and boundary conditions, with worst-case simulation and enough repeats for reliable results
Process and cleaning validationProduction, QC and QA execute and approve according to the VMP
Continued process verificationQA and production review the process data on a routine basis

Preventive maintenance, calibration, change control, revalidation and annual product review are the ongoing systems that keep the validated state. The team links to cleaning method validation and water system validation for these two programmes.

Role-by-Role Duties (RACI)

A responsibility matrix in the VMP names who prepares, reviews and approves each document. The matrix below is a common practice and is not tied to a regulation.

DocumentPreparesReviewsApproves
VMPValidation coordinatorProduction, engineering, QCQA, validation, production and engineering
ProtocolValidation or engineering teamQA, production, QCQA manager
Execution recordWorking groupTask-force memberQA
ReportValidation teamProduction, QCQA manager

QA approval stays independent of execution, so the QA representative who approves a report does not execute the tests in it.

Change Control, Deviations and Revalidation

Any out-of-limit result during execution must be raised as a deviation. It must be investigated before a retest. The task force approves validation change control, and QA must be involved in every change, while revalidation is decided by the task force, based on the change control and the risk assessment.

The Pharmaceutical Inspection Co-operation (PIC/S) document PI 006-4 (published 2 August 2026, in force 1 October 2026) replaces PI 006-3. According to a secondary summary, it calls for QA involvement in all change controls. It also places validation deviations in the site deviation system and replaces periodic revalidation with ongoing process verification.

Data Integrity, CSV and AI Accountability

An IT/CSV representative should join the working group whenever a computerised system is validated. According to the same summary of PI 006-4, the data integrity of a test must be confirmed by a person who did not execute it. The draft EU GMP Annex 11 (consultation 7 July to 7 October 2025) stresses access control, audit trails, qualification and validation, and supplier management. A 2026 FDA warning letter held a firm accountable for skipped process validation and for AI-generated documents that were not reviewed, so the quality unit must review such documents for accuracy and cGMP compliance before use.

Vendors and Contract Laboratories

Quality control of a project starts with the pre-qualification of suppliers and contractors. It includes named team members with QC duties, QC audits and checkpoints, FAT and pre-installation meetings. Vendor FAT and SAT support the site IQ and OQ, but they do not replace them unless the company has assessed and approved them. QA of the company keeps the responsibility for vendor work.

Training, Authority and Inspection Readiness

Every team member should have a training record for the validation tasks assigned. The task team must have the authority to approve or reject validation documents, otherwise the quality unit cannot meet its written responsibilities. Warning letters often cite 21 CFR 211.22, and a process that is not validated before distribution is cited as a the guidance violation.

Precautions

  • The VMP must be updated whenever the team structure or scope changes.
  • A person must not approve validation work that the same person executed.
  • Vendor documents must be reviewed by QA before they are accepted.

Revision History

VersionChange
CurrentRegulatory basis, RACI, lifecycle duties

Related Post: Fundamentals of Validation SOP

References

  1. EudraLex Volume 4, European Commission
  2. Process Validation: General Principles and Practices, US FDA
  3. What FDA Warning Letters Tell Us About GMP Compliance, Pharmaceutical Online
  4. PIC/S PI 006-4 summary, GMP Insiders
  5. Drafts of EU GMP Annex 11, Annex 22 and Chapter 4, ECA Academy
  6. What FDA’s AI Warning Letter Tells Us About GMP Accountability, Pharmaceutical Technology
  7. ICH releases revised Q9 guideline, RAPS
  8. Validation site floor Standard Operating Procedure.
  9. Validation Standard Operating Procedure (Validation Master Plan), sections 2 and 5 (our floor SOP ans procedure)
  10. 21 CFR 211.22

Leave a Comment