AHU Installation Qualification (IQ) Protocol: Complete Guide with Format & Checklist

AHU Installation Qualification (IQ) Protocol Objective: The objective of this protocol is to verify that the AHU is installed as per approved design specifications, drawings, and manufacturer recommendations. This AHU Installation Qualification (IQ) Protocol covers the following:

SERIAL NO.ITEM DESCRIPTION
1.0Identification and inspection of the contact surfaces and non-contact surfaces
2.0OVERVIEW:
2.1Objective
2.2Purpose
2.3Scope
2.4Responsibility
2.5Execution Team
3.0ACCEPTANCE CRITERIA
4.0REVALIDATION
5.0INSTALLATION QUALIFICATION PROCEDURE
5.1System Description
5.2Instructions for Filling the Checklist
5.3Installation Check-List
5.4Identification Of Major Components
5.5Identification, classification, and verification of process control instruments
5.6Identification and inspection of utilities
5.7Identification and inspection of the contact surfaces and non-contact surfaces
5.8Identification of Safety Feature(s)
5.9Verification of Drawing and Documents
5.10Abbreviations
5.11Deficiency And Corrective Action(s) Report(s)
5.12Annexure(s)
6.0INSTALLATION QUALIFICATION FINAL REPORT
6.1Summary
6.2Conclusion
6.3Final report approval
AHU installation qualification checklist showing equipment setup verification in pharma cleanroom
1.0PROTOCOL APPROVAL:

Signing of this approval page of Protocol indicates agreement with the qualification approach described in this document. If modifications to the qualification approach become necessary, an addendum shall be prepared and approved. The protocol cannot be used for execution unless approved by the following authorities.

This Installation Qualification protocol of Air handling unit has been reviewed and approved by the following persons:

XYZ Pharmaceutical:

FUNCTIONNAMEDEPARTMENTSIGNATUREDATE
PREPARED BY QUALITY ASSURANCE  
REVIEWED BY PROJECTS / ENGINEERING  
REVIEWED BY PRODUCTION  
APPROVED BY QUALITY ASSURANCE  

Service Company name:

NameDesignationSignatureDate
      
2.0OVERVIEW:
  2.1OBJECTIVE: 
 The objective of developing and executing this protocol is to collect sufficient data pertaining to the Air handling system and define the qualification requirements and acceptance criteria for the unit. Successful completion of these qualification requirements will provide assurance that the Air handling system was installed as required in the service area. Installed components should comply with the engineering design, and specification of the equipment and Vendor recommendations. To ensure that appropriate interconnections are made for utilities /equipment before starting installation qualification. Ensure that the system meets the cGMP and Regulatory requirements.  
2.2PURPOSE:
       The purpose of this protocol is to establish documentary evidence to ensure that the Air handling system received matches the Design specification and also to ensure that it is properly and safely installed.  
2.3SCOPE:
 The installation qualification protocol shall be followed for AHU of manufacturing facility at XYZ Pharmaceuticals (Location).

This protocol defines the methods and documentation that shall be used to evaluate the system installation in accordance with the specifications and intended use. Successful implementation of this protocol shall verify that the systems installed meet the requirements specified.

Installation checks shall be performed to document that all the components of the systems are installed with proper supporting services and utilities. All documentation, including manufacturer’s manuals for the components described in this protocol shall be verified for availability. Any exceptional conditions encountered during the qualification studies shall be identified for review. Exceptional conditions shall be investigated and the appropriate course of action determined. All data shall be documented.
2.4RESPONSIBILITY: 
 The following shall be responsible; Quality Assurance Officer/Executive – For preparation of protocol Projects / Engineering Head – For execution  Production Head – For execution support Quality Assurance Head – For adequacy and final approval
2.5EXECUTION TEAM:
 The satisfactory installation of the Air handling system shall be verified by executing the qualification studies described in this protocol. The successfully executed protocol documents that the Air handling system is installed and is satisfactorily integrated. Execution team is responsible for the execution of installation of Air handling system. Execution team comprises of:
DEPARTMENTDESIGNATIONNAMESIGNATUREDATE
PROJECTS / ENGINEERING    
PRODUCTION    
QUALITY ASSURANCE    
3.0ACCEPTANCE CRITERIA:
1The AHU shall meet the system description given in design qualification.
2The AHU shall meet with the acceptance criteria mentioned under the topic “Identification of major components”.
4.0REVALIDATION CRITERIA:
 The machine has to be revalidated if:
 If there are any major changes in system components which affect the performance of the system, after a major breakdown, maintenance activity. As per revalidation date and schedule.
5.0INSTALLATION QUALIFICATION PROCEDURE:
5.1HVAC SYSTEM DESCRIPTION

Air handling unit is a closed system which re-circulates air free from particulate matter to different areas. Following parts are installed in the system.

  1. AHU Body
  2. Pre-Filter
  3. Heating coil
  4. Cooling Coil
  5. Blower
  6. Motor
  7. Secondary Filter
  8. Supply Air Housing Box and Perforated Sheet
  9. Return Air Riser
  10. HEPA Filter
  11. GI Ducting
  12. Insulation

This is a closed box-type construction having a chamber for mixing the fresh and the return air.  The fresh air is made to pass through the 10m  & 5m filter. The Cooling and Heating coils are fixed in the system to maintain Relative Humidity % and temperature at the place of intended use. 

The system is provided with damper in fresh air duct and return air duct so that the system can supply the desired quantity and quality of air at the designated areas.

 Instrumentation Details:

  1. Differential pressure transmitter
  2. VFD
  3. Filter condition monitoring sensor
  4. Chilled & Hot water control valves 
  5. Chilled air sensor after cooling coil
  6. Temperature and RH sensor

Filters:

  •  The pre-filter is made of synthetic washable material having 10m  + 5m rating, and has filtration efficiency of 90% down to 10m and 90% down to 5m filter.
  • The Fine Filter has a 3 m rating and has a filtration efficiency of 99%.
  • The HEPA Filter is having 0.3m rating, with an efficiency of 99.97%.

The total volume of air is supplied to the different areas by supply duct, which is made up of G.I. sheet of 24-gauge thickness. The returned air is suck back through the return air duct network.

Auto Control Valve

The auto control valve operates so as to maintain the desired temperature and Relative Humidity % in the area of intended use in the designated place. The valve automatically controls the flow of chilled and hot water in the cooling and heating coils.

Air Handling Units:

The double-skinned AHU consists of double-skinned panels with anodized extruded aluminium sections. Framework bolted together with a sandwich panel having 24 gauge G.I. pre-coated for outer and 20 gauge G.I. plain for inner skin .50 mm thick PUF to be injected between the two panels. Drain tray is of 18 gauge S.S 304.

Air distribution:

Air distribution is enabled by GSS supply and return air ducts. The supply air duct joints are sealed with Silicon sealant. Flange joints are provided with 3 mm thick Neoprene gasket. Air supplied into the rooms through supply air terminal filters to achieve good air distribution and is returned through low-level GSS return air risers with down to 10 m return air filters. The slab-mounted supply terminals are of the bottom-loading type.

Supply air terminal HEPA Filters:

For all the critical areas, conditioned and filtered air is supplied to the room through terminal HEPA filters (0.3 micron 99.97% efficiency).

Return air Riser:

For all the critical areas, return air risers are provided to collect the air from just above the floor level for better dust removal.

Duct leakage test:

The smoke testing to be conducted for detecting the duct leakage.

Piping system:

Mild steel  ‘C’ class pipes are used for entire chilled water. Drain pipes are GI ‘B’ class. Butterfly / Gate valves are provided at all AHU coils required to facilitate shut-off for servicing. Controls valves are provided with all coils for the chilled water & hot water flow. ‘Y’ Strainers are also provided in chilled & hot water supply lines.

Purge air system:

The purge air is to be collected by global exhaust unit, which is provided separately for XYZ block. This purge air unit system has heat recovery system to gain energy from the purge air.

Insulation:

The supply air ducts and return air ducts are insulated respectively with 16 mm and 9 mm PUF. The chilled supply /return water pipes are insulated with 25 / 19 mm thick nitrile rubber. All insulated hot water pipes are clad with 24-gauge aluminium cladding.

Reviewed By:

Date:

5.2INSTRUCTION FOR FILLING THE CHECKLIST
1In case of the compliance of the test, use the word ‘Complies’; otherwise, use ‘Does not comply‘ to indicate non-compliance.
2For identification of the components of the equipment and utilities, use the word ‘’yes’’ to show its presence and use ‘No’ to indicate the absence of the identity.
3Give the detailed information in the summary and conclusion part of the Installation Qualification report.
4Whichever column is blank or not used, ‘NA’ shall be used.
5Put (tick mark) wherever applicable.

5.3 INSTALLATION CHECKLIST for AHU Installation Qualification (IQ) Protocol

Sr.No.StatementYes/NoChecked ByDate
1Verify that the “as-built drawings” are complete and represent the design concept.
2Verify that major components are securely anchored and shock-proof.
3Verify that there is no observable physical damage.
4Verify that there is sufficient space for maintenance, as provided.
5Verify that all electrical connections have been made.
6All access parts are examined and cleared of any debris.
7Required electric connections are tight, weather-proof, and earthed.
8Verify that identification nameplate is visible.
9Units installed on foundation and secured in place as per manufacturer’s recommendations.
10Ensure AHU outer skin is made up of green colored GI material.
11Dampers are installed as indicated in the air flow diagram and are easily operable.
12Fresh air damper
13Supply air damper
14Return air damper
15Verify supply and return air duct routing to each room is as per ducting layout diagram.
16Check grills are installed in each room as per ducting layout diagram.
17Service lines like chilled water and hot water are connected to AHU system as indicated in line diagram.
182-way proportioning control valve is installed in chilled water return line as shown in schematic piping diagram.
193-way proportioning control valve is installed on hot water return line as in schematic diagram.
20Valves on chilled water service lines are installed correctly as per direction indicated in schematic diagram, are easily operable, and connected to BMS.
21Valves on hot water service lines are installed correctly as per direction indicated in schematic diagram, are easily operable, and connected to BMS.
22All joints of piping, ducting, AHU body, and blower are properly sealed.
23Check the motor provided is flame proof / non-flame proof.
24Variable Frequency Drive (VFD) is installed as per design specification.
25Check DDC panel is installed and is connected to VFD.
26Ensure following components are provided with earthing: a) Motor, b) VFD.
27Verify that PO is available and copy of the same is attached.

Reviewed By:

Date:

5.4IDENTIFICATION OF MAJOR COMPONENTS:
 Describe each critical component, check them, and fill in the inspection checklist.
System ComponentsDesign SpecificationComplies / Does Not ComplyMethod of VerificationChecked By Sign / Date
A) Air handling unit: Construction details
Make   
TypeDouble skin floor-mounted   
Frame structureExtruded profile Aluminium, Anodised with thermal break.   
Dimension (Lx W x H)3470x 1540×3000 mm   
 Panel43±0.5 mm thick sandwich type   
 Inner skin20 gauge GI Plain   
Outer skin24 Gauge G.I. precoated   
InsulationPolyurethane   
Panel lockLow projection, hand-operated, Aluminium construction.   
Handle‘C’ type Aluminium   
HingesNylon die cast with S.S. pivot   
DampersOppose blade Aerofoil design, low leakage, aluminium anodized.   
Drain pan1.2mm thick S.S. 304   
Vibrator isolator below AHUShall be provided with antivibration pad below AHU.   
System ComponentsDesign SpecificationComplies / Does Not ComplyMethod of VerificationChecked By Sign / Date
1. Fan
TypePlug type   
Make   
Diameter450 RD   
Fan speed RPM2910   
2. Motor15 HP -2 Pole, 3Ph., Sq.Cg in Non-FLP Construction, RPM 2895   
Make   
3. Filters
Make   
Pre Filter90% down to 10 micron+ 90% down to 5 micron combination   
5 micron bag filter Size-Qty592X592X500 –4No   
10 micron filter Size-Qty592X592X50 –4No   
Secondary filter99% – 3 micron   
Size-Qty & Type610 x 610 x 305-4No. Flange type   
4. Coils
Chilled water coil size12.5” H x 48” L -6RD   
Hot water coil size12.5” H x 48.0” L -2 RD   
5. Ductings
TypeRectangular / Square   
MOCGSS   
Thickness24 mm   
System ComponentsDesign SpecificationComplies / Does Not ComplyMethod of VerificationChecked By Sign / Date
Type of insulationPUF, 16/9 mm   
Pressure testingTo be carried out and report to be enclosed   
Type of sealantGE 2000   
MOC dampersAluminium   
No. of supply air dampers    
No. of return air dampers    
 Type of duct supportsMS, 40 mm. angle supported to the ceiling   
Type of flange to flange connectionsMilled steel flange connection. Sealing to be done with rubber gasket, and the duct flanges shall be tightened with GI nuts and bolts.   
6. Return air risers
Make   
Type of mountingVertical   
Size    
MOCMS powder coated   
Thickness of the riser sheet18 SWG   
Quantity of riser    
Clearance between floor and riser8 inch   
Riser filter size    
Efficiency90%   
System ComponentsDesign SpecificationComplies / Does Not ComplyMethod of VerificationChecked By Sign / Date
Quantity of diffusers    
No. of grills    
Size of grill    
7. Hot water piping
Size of header80 mm   
Size of tapping    
Type of inlet valveBF/Ball valve   
Type of outlet valveBF/Ball valve   
Type of insulationRock wool aluminium cladding   
Thickness of insulation50 mm   
8. Chilled water piping
Size of header125 mm   
Size of tappingAs per enclosed piping drawing   
Type of inlet valveBF/Ball valve   
Type of outlet valveBF/Ball valve   
Type of insulationNitrile rubber   
Thickness of insulation19 mm   
9. Pressure testing of pipelines
Hot waterReport to be enclosed   
Chilled waterReport to be enclosed   
10. Electrical and control system
Location of control panelService floor   

5.5 IDENTIFICATION, CLASSIFICATION & VERIFICATION OF PROCESS CONTROL INSTRUMENTS:

Process control instruments are Indicators, Sensors, Controllers, and Gauges. These are classified into two categories.

  1. Critical (C): The instruments whose performance will directly affect the quality parameters of the product.
  2. Non – critical (N): The instruments whose performance failure will not affect product quality and which are used for process control.
InstrumentsCheckObservationClassChecked byDate
Temperature & RH Indicator  Check for any physical damage    
Make 
Range details 
Differential Pressure Transmitter  (Across Rooms)Check for any physical damage    
Make 
Range details 

5.5 IDENTIFICATION & INSPECTION OF UTILITIES:

The utilities required are identified on the basis of information available in Design qualification document, information brochure, and purchase order.

UtilityRequirementPurposeVerified by
Power   
Chilled water   
Hot water   

5.6 IDENTIFICATION & INSPECTION OF THE CONTACT SURFACES & NON CONTACT SURFACES

In this section, all components of the equipment, which may come into direct/indirect contact with the product, are probably affecting the product’s safety, purity, and efficacy.

Contact surfaces are listed based on Physical inspection, Instruction manuals, drawings, and Design qualification documents.

CONTACT SURFACES

ComponentSpecified MOCObservationMethod of verificationChecked by
AHU Housing  Double Skin Type PUF insulated, made out of GI inside and outside, powder coated.   
Pre Filters  Non-Woven synthetic media, one side HDPE mesh with Aluminum casing   
Secondary Filters  Non-woven synthetic media, one side HDPE mesh with Aluminium casing   
DuctsGalvanized Iron   
HEPA Filters  Micro glass fiber paper, aluminum separator   

Comments:

Reviewed By:

Date:


5.8
IDENTIFICATION OF SAFETY FEATURES:
 Identify and record the safety features (if any) and their function in following tables:
Safety Features DescriptionFunctionIdentified By (Sign)Date
1. Earthing of motorTo avoid accidents due to the leakage current.  
2. Insulation of hot surfaceTo avoid burn injury.  
3. Door limit switchTo avoid accidents during operation  

Reviewed By:

Date:

5.9VERIFICATION OF DRAWING AND DOCUMENTS:
 Following documents are reviewed and attached as listed below:
Sr. No.DRAWING AND DOCUMENT DETAILCHECKED BY (SIGN)DATE
 Air flow diagram of  AHU  
 Ducting layout  
 Piping layout and Instrumentation layout  
 Risers layout  
 Pressure differential datasheet  
 AHU hot water manifold drawing  
 AHU chilled water manifold drawing  
 Design datasheet  
 AHU GA drawing  
 Leak test for duct  

Reviewed By:

Date:

5.10ABBREVIATIONS
 Following Abbreviations are used in the installation qualification protocol of Air handling unit
 AHU: Air Handling Unit
HEPA: High efficiency particulate air
HVAC: Heating, ventilation, and air conditioning CFM: Cubic feet per minute
MOC: Material of construction
GI: Galvanized iron
PVC: Polyvinyl chloride
RPM: Rotation per minute
BHP: Break Horse Power
SA:  Supply air                           
RA: Return air
DOP: Dioctyl pthalate
SWG: Standard wire gauge
VFD: Variable frequency drive
GSS: Galvanized stainless steel 
PUF: Polyurethane Foam
HDPE: High-density polyethylene
DDC: Direct Digital controller
5.11DEFICIENCY AND CORRECTIVE ACTION (S) REPORT (S)
Following deficiency was identified and corrective actions taken in consultation with the validation team.
Description of deficiency:
 
 
 
 
 
 
 
Corrective action(s) taken:
 
 
 
 
 
 
 

Reviewed By:

Date:

5.12   Annexure:

Sr.No.Annexure No.Annexure Details  
     
     
     
     
     
6.0INSTALLATION QUALIFICATION FINAL REPORT:
All the IQ data sheets and discrepancy reports shall be reviewed by validation team to prepare summary report. The summary of IQ shall be used to draw conclusion for approval of installation qualification report.
6.1SUMMARY
 
 
 
 
 
 
 
6.2CONCLUSION
 
 
 
 
 
 
 

Reviewed By:

Date:

6.3 FINAL REPORT APPROVAL

It has been verified that all tests required by this protocol are completed, reconciled, and attached to this protocol or included in the qualification summary report. Verified that all amendments and discrepancies are documented, approved, and attached to this protocol.

Signature in the block below indicates that all items in this qualification report of air handling unit have been reviewed and found to be acceptable and that all variations or discrepancies have been satisfactorily resolved.

NAMEDESIGNATIONDEPARTMENTSIGNATUREDATE
  PROJECTS / ENGINEERING  
  PRODUCTION  
  QUALITY ASSURANCE  

Leave a Comment