GMP & Pharmaceutical Manufacturing Expert
✓ Reviewed by: Pankaj Sharma - Quality Control Specialist
Reviewed for QC, QA accuracy, laboratory practices, analytical methods, and technical Documents
📅 Last Updated: November 13, 2026
About this SOP: The SOP on operation and cleaning of the decontamination autoclave covers the utility pre-checks, the vacuum leak test run first (weekly, at the frequency the site defines), a Bowie and Dick test (daily before the first load, varying by manufacturer), the standard or HPHV cycle, daily chamber cleaning with 70% v/v IPA, and recording with the attached strip chart.
1.0 Objective
This SOP is a procedure that lays down the operation and cleaning of the decontamination autoclave, a PLC-controlled steam unit used in Production to decontaminate used and rejected materials before washing or disposal.
2.0 Scope of the SOP on operation and cleaning of the decontamination autoclave
This SOP applies to the PLC/MMI-controlled decontamination autoclave in the Production facility. It covers the vacuum leak test and the Bowie and Dick test, and also the standard and HPHV cycles. Loading, cleaning and records are included too. Calibration detail is given in the SOP on operation and calibration of autoclave.
3.0 Responsibility
This section names the roles that run, supervise, maintain and review the autoclave.
3.1 The trained operator shall run the cycle and fill the log book.
3.2 The supervisor shall supervise the process and check the record.
3.3 Engineering shall rectify any breakdown and maintain the calibration status.
3.4 Manager Production shall be responsible for training and implementation of the SOP.
3.5 Head Quality Assurance (QA) or designee shall ensure that the SOP is followed, review the cycle records and verify the decontamination records.
4.0 Accountability
Manager Production is accountable for the correct implementation of this SOP in the department, and Head QA or designee is accountable for its compliance. The plant’s own job titles shall be used in the controlled copy.
READ ALSO
SOP for Cleaning and Operation of Leak Test Apparatus for Filled Bottles in Liquid Department
1.0 OBJECTIVE: To lay down the procedure for the Cleaning and Operation of leak test…
5.0 Procedure
The procedure covers loading, start-up, the four cycles, failure handling, cleaning, records, maintenance and qualification, in the order the work is done.

5.1 Loads and loading
The autoclave may be used for the loads below, each with its own load pattern given in the loading procedure.
| Load | Preparation |
|---|---|
| Used filling accessories (product to product change-over) | Washed and loaded as per the validated load pattern |
| Glassware | Filled with WFI followed by 1 N NaOH, with loose caps |
| Rejected vials and syringes | Loaded in biohazard bags |
| Contaminated garments | Loaded in biohazard bags |
| Treated expired active raw material | Treated first, then loaded |
5.1.1 The operator shall load the chamber only as per the validated load pattern in Annexure-1 of the loading procedure.
5.1.2 Biohazard bags must be left slightly open and bottle caps must be fitted loose, so that air can leave and steam can enter the load, and loose caps also prevent breakage.
5.1.3 After the cycle, the hot materials shall be unloaded carefully and sent for washing or disposal.
5.2 Operation
5.2.1 The operator shall switch ON the panel MCB switch located on the internal side of the panel.
5.2.2 Then the control key shall be switched ON from the panel, so that the PLC starts and the LCD is displayed on the MMI.
5.2.3 Before operation, the operator must ensure that all manual utility valves on the lines are open and that the gauges show not less than the following pressures.
| Utility | Minimum pressure |
|---|---|
| Plant steam | 1.5 Kg/cm² |
| Pure steam | 1.5 Kg/cm² |
| Compressed air | 6.0 Kg/cm² |
| Soft water | 1.2 Kg/cm² |
5.2.4 Press F6 on the MMI; the main menu appears on the LCD.
5.2.5 The main menu has the following keys.
| Key | Function |
|---|---|
| F1 | Set View Parameter |
| F2 | Login |
| F3 | Monitor Screen |
| F4 | Start-up Screen |
| F5 | Batch Data |
| F6 | Print Alarm History |
| F7 | Clear Alarm History |
5.2.6 Press F4 (Start-up Screen) to open the start-up screen; ‘PLEASE SELECT PROCESS’ is displayed on the LCD together with the following keys. The screen names and F-keys are those of this autoclave’s MMI and follow the equipment’s own manual.
| Key | Function |
|---|---|
| F3 | Select Process |
| F2 | Print Parameter |
| F1 | Start Process |
| F4 | Abort |
| F5 | Process end ACK |
| F6 | St Door Unlock |
| F8 | Main Screen |
5.2.7 Select the process by pressing F3 on the MMI. The vacuum leak test is the first process shown, at the top of the LCD, and is not one chosen beforehand.
5.2.8 Before starting any process, close the door and confirm that the ‘Door precondition’ indicator is lit, because a lit indicator means the door is closed correctly.
5.2.9 Switch to the strip chart recorder and press the record button before the process starts; temperature and pressure are then displayed on the screen.
5.3 Common cycle steps
Every cycle follows the same sequence of keys. Only the selected process and the parameter set differ.
| Stage | Key and action |
|---|---|
| Select | F3, select the process |
| F2, print the set parameters | |
| Check | Compare the printout with the Annexure-1 set of the same process |
| Start | F1, start the process |
| Monitor | F8 for the main menu, then F3 for the monitor screen (temperature, pressure, phase and elapsed time) |
| End | ‘PROCESS END’ is displayed on the LCD |
| Acknowledge | F1 for process end acknowledge (as listed in the original procedure steps) |
The standard cycle has no pre-vacuum and holds 121.4 °C for 30 min. The HPHV (high pressure high vacuum) cycle adds a pre-vacuum, 3 pre-pulses and a post vacuum held for 20 min. The hold is the same, and these are one plant’s validated settings. They are given in Annexure-1.
5.4 Vacuum leak test
5.4.1 Press F2 to print the set parameters of the vacuum leak test.
5.4.2 Check the printed parameters against the vacuum leak test set in Annexure-1.
5.4.3 Press F1 to start the process.
5.4.4 Press F8 to go to the main menu.
5.4.5 Press F3 to go to the monitor screen, where the temperature, pressure, phase of the process and elapsed time are displayed on the LCD.
5.4.6 At the end of the process, the LCD displays ‘PROCESS END’.
5.4.7 Press F1 to acknowledge the process end.
5.4.8 Run the vacuum leak test before any other cycle at the frequency defined by the site; it is typically weekly, and the frequency varies by manufacturer.
5.5 Bowie and Dick test
5.5.1 Select the ‘BOWIE AND DICK’ test by pressing F3 on the MMI.
5.5.2 Press F2 to print the set parameters of the Bowie and Dick test.
5.5.3 Check the printed parameters against the Bowie and Dick set in Annexure-1 (pre-vacuum -0.600 bar, pre-pressure 0.600 bar, 3 pre-pulses, heat-up 110/115/119 °C).
5.5.4 Press F1 to start the process.
5.5.5 Press F8 to go to the main menu.
5.5.6 Press F3 to go to the monitor screen, where the temperature, pressure, phase of the process and elapsed time are displayed.
5.5.7 At the end of the process, the LCD displays ‘PROCESS END’.
5.5.8 Press F1 to acknowledge the process end.
5.5.9 Perform the Bowie and Dick test to check the air removal system of the chamber at the frequency defined by the site; it is typically daily, before the first load, and the frequency varies by manufacturer.
5.6 Standard process
5.6.1 Select the ‘STANDARD PROCESS-‘ by pressing F3 on the MMI.
5.6.2 Press F2 to print the set parameters.
5.6.3 Check the printed parameters against the standard process set in Annexure-1 (hold 121.4 °C for 30 min, control band 0.2 °C, overshoot limit 124.0 °C).
5.6.4 Press F1 to start the process.
5.6.5 Press F8 to go to the main menu.
5.6.6 Press F3 to go to the monitor screen, where the temperature, pressure, phase of the process and elapsed time are displayed.
5.6.7 At the end of the process, the LCD displays ‘PROCESS END’.
5.6.8 Press F1 to acknowledge the process end.
5.7 HPHV process
5.7.1 Select the ‘HPHV PROCESS-‘ by pressing F3 on the MMI.
5.7.2 Press F2 to print the set parameters.
5.7.3 Check the printed parameters against the HPHV set in Annexure-1.
5.7.4 Press F1 to start the process.
5.7.5 Press F8 to go to the main menu.
5.7.6 Press F3 to go to the monitor screen, where the temperature, pressure, phase of the process and elapsed time are displayed.
5.7.7 At the end of the process, the LCD displays ‘PROCESS END’.
5.7.8 Press F1 to acknowledge the process end.
5.8 Cycle failure and troubleshooting
When a test or a cycle fails, the operator must act as shown below, and the numerical limits are those given in Annexure-1.
| Event | Action |
|---|---|
| Failed vacuum leak test | Do not run a load, inform Engineering and QA, and repeat the test after correction |
| Failed Bowie and Dick test | Do not use the unit until the air removal system is checked |
| Aborted cycle | Do not unload the load as decontaminated, record a deviation and repeat the cycle |
| Alarm, including an overshoot alarm | Acknowledge the alarm and record the reason in the log book |
5.9 Cleaning
The chamber is cleaned daily and after any spillage, and the outside of the unit is wiped with the same agent.
5.9.1 Clean the chamber once a day before the vacuum leak test, and also after any spillage during a cycle, using filtered IPA 70% v/v with a soft lint-free mop.
5.9.2 Wipe the external surfaces with IPA 70% v/v.
5.9.3 The cleaning shall be recorded.
5.10 Records and reporting
Each cycle is recorded in the log book, and the printed strip chart is attached to the record.
5.10.1 After the cycle, the operator shall record the details in the log book (Annexure-2): date, cycle No., load pattern, material loaded, hold start and end time, done by, checked by and remarks.
5.10.2 The printed strip chart with the stamp shall be attached to the record, because it is the printed evidence of temperature and pressure for the cycle.
5.10.3 Any abort or alarm shall be recorded, and a deviation shall be raised.
5.10.4 QA shall verify the decontamination records, as is also done during campaign change-over.
5.11 Maintenance and calibration
Engineering maintains the unit and also keeps its safety devices in calibration.
Engineering checks the gasket and door seal, cleans the drain and filter, and keeps the safety valve and gauges in calibration. A breakdown must be reported to Engineering, and the equipment returns to use only after cleaning and release by QA or Production. Calibration detail is in the SOP on operation and calibration of autoclave. This SOP fixes no frequencies, which follow the manufacturer’s manual.
5.12 Qualification and verification
The autoclave is qualified under EU GMP Annex 15 (installation qualification (IQ), Operational Qualification (OQ) and Performance Qualification (PQ), including heat distribution and penetration with the load patterns). Load patterns are verified with Geobacillus stearothermophilus biological indicators placed at the hardest-to-heat locations, together with thermocouples and chemical indicators. The World Health Organization (WHO) Laboratory Biosafety Manual, 4th edition (2020), expects validated decontamination methods with periodic checks against the manufacturer’s specification. EN 285 excludes equipment for biological waste, so waste autoclaves run on validated site cycles. Annex 11 applies to the PLC/MMI records, and its revision was published only as a consultation draft in July 2025.
6.0 Precautions
The precautions below protect the operator from heat, steam, broken glass, sharps and hot caustic liquids.
6.1 Operators must wear safety goggles and gloves during operation, and heat-resistant gloves for hot loads.
6.2 A mask must be worn where hot Water for Injection (WFI) or NaOH is handled.
6.3 Glass breakage and sharps in rejected vials and syringes can cause injury, so these must be handled with care.
6.4 Maintain a distance during opening and closing of the door, and open it only after the chamber has depressurised.
7.0 Abbreviations
The table lists every abbreviation used in this SOP with its full form.
| Abbreviation | Full form |
|---|---|
| SOP | Standard Operating Procedure |
| PR / PRD | Production |
| QA | Quality Assurance |
| LCD | Liquid crystal display |
| PLC | Programmable logic controller |
| MMI | Man and machine interface |
| HPHV | High pressure high vacuum |
| IPA | Isopropyl alcohol |
| WFI | Water for injection |
| NaOH | Sodium hydroxide |
| MCB | Miniature circuit breaker |
| ACK | Acknowledge |
| GMP | Good manufacturing practice |
| WHO | World Health Organization |
| IQ / OQ / PQ | Installation, operational and performance qualification |
8.0 References
The documents below govern this SOP. The copy is distributed to Production, QA, Engineering and Microbiology.
8.1 Operating manual of the decontamination autoclave.
8.2 SOP on operation and calibration of autoclave.
8.3 Procedure for preparation, issuance, revision, retrieval, obsolescence and destruction of SOPs.
8.4 Distribution: Production, QA, Engineering and Microbiology.
Related SOP: Operation and Calibration of Autoclave
9.0 Annexures
The annexures give the set values of each process and the blank log book format.
Annexure-1: Standard parameters (one plant’s settings, to be applied as per the validated recipe)
| Process | Set values |
|---|---|
| Vacuum leak test | Pre-vacuum -0.700 bar, delay before hold 3 min, hold 10 min, acceptable leakage 0.013 bar, end pressure -0.060 bar |
| Bowie and Dick | Pre-vacuum -0.600 bar, pre-pressure 0.600 bar, 3 pre-pulses, heat-up 110/115/119 °C, holds 5/4/3 min, heat-up band 0.5 °C, small valve set point 120 °C |
| Standard | No pre-vacuum or pulses, heat-up 110/115/119 °C, hold 121.4 °C for 30 min, control band 0.2 °C, overshoot 124.0 °C, stop 120.0 °C, reset 119.0 °C, end at 0.050 bar and 105 °C, chamber pressure high 1.500 bar |
| HPHV | Pre-vacuum -0.500 bar, pre-pressure 0.500 bar, 3 pre-pulses, heat-up 100/110/119 °C, hold 121.4 °C for 30 min, post vacuum -0.500 bar held 20 min, 1 post pulse, end at -0.068 bar and 100 °C |
Annexure-2: Log book for decontamination autoclave
| Date | Cycle No. | Load Pattern | Material Loaded | Hold Start Time | Hold End Time | Done By | Checked By | Remarks |
|---|---|---|---|---|---|---|---|---|
10.0 Revision History
The table records each revision of this SOP with its effective date and reason.
| Revision No. | Effective Date | Reason for revision |
|---|---|---|
| 00 | DD/MM/YYYY | New SOP |
References
- EudraLex Volume 4 (Annex 1, Annex 11, Annex 15), European Commission
- Laboratory biosafety manual, 4th edition, WHO, 2020
- Biohazardous Waste Decontamination in an Autoclave, STERIS Life Sciences
- BS EN 285 large steam sterilizers, BSI, 2015

Naresh Bhakar is the Founder and Author at Pharmaguddu.com, bringing his extensive expertise in the field of pharmaceuticals to readers worldwide. He has experience in Pharma manufacturing and has worked with top Pharmaceuticals. He has rich knowledge and provides valuable insights and data through his articles and content on Pharmaguddu.com. For further inquiries or collaborations, please don’t hesitate to reach out via email at [email protected].